Officials to be failed to meet with the rules of Central Public Works Department

In March 2013, The work pertaining to the proposed government school in Sector 49 was allocated to a contractor which was to be completed within 18 months. In August 2011 an estimate of Rs 6.48 crore was prepared and detailed notice inviting tender was approved for Rs 5.43 crore by the UT chief engineer. But the project gets failed due to delay in completion of a project and cost escalation from Rs 6.48 crore to Rs 11.83 crore.